Completed project
Private Villa Swimming Pool & Waterproofing Project – Irbid, Jordan
Irbid · 2020 · 8 × 18 m pool and Jacuzzi
PROJECT OVERVIEW
The project, from brief to delivery.
Completed in 2020, this private residential project in Al-Asha, Irbid, included comprehensive waterproofing and swimming pool construction works. The scope included waterproofing the building foundations and a 400 m³ underground water reservoir, together with the complete civil and mechanical construction of an 8 × 18 m swimming pool and a 3 × 4 m Jacuzzi.
Scope of work
- Building foundation waterproofing
- 400 m³ water reservoir waterproofing
- 8 × 18 m swimming pool civil works
- Complete pool mechanical works
- 3 × 4 m Jacuzzi construction
- Pool and Jacuzzi waterproofing
- Plumbing and circulation system installation
- Testing and commissioning
DELIVERY JOURNEY
How the project came together.
- 01
Foundation & reservoir waterproofing
Waterproofing of the building foundations and the 400 m³ underground water reservoir.
- 02
Pool & Jacuzzi structure
Civil construction of the 18 × 8 m pool and 4 × 3 m Jacuzzi.
- 03
Waterproofing systems
Coordinated waterproofing for the pool, Jacuzzi and critical construction details.
- 04
Mechanical installation
Installation of plumbing, circulation, sand filtration and the 60 kW heating system.
- 05
Testing & commissioning
Testing, commissioning and preparation of the completed systems for handover.